Drone aerial view of concrete armour unit installation on the offshore breakwater at Port-La-Nouvelle, France

Témoignage – Bouygues port La Nouvelle

L’entreprise Bouygues a fait appel en urgence à CLAS pour lapose des blocs artificiels la digue offshore a été détruite trois fois par les tempètes hivernale et avec les proc´dures et équipements mis en oeuvre, POSIBLOC™, sonar multifaisceaux et jumeaux numérique, le chantier n’avançait pas. Après 18 mois d’efforts soutenus la digue offshore restait très…

Concrete armour units stored on a barge prior to installation on a port breakwater

Testimonial – Van Oord, Constanta breakwater(Roumanie)

Van Oord appointed CLAS to provide technical support on the Constanța port extension project in Romania. During the Constanța port protection project in Romania, CLAS teams worked alongside Van Oord, providing specialized support for the installation of ACCROPODE™II concrete armour units and independent certification of the breakwater armour layer. The mission entrusted to CLAS Technical…

Groupe de cinq blocs cassés visibles sur la digue de la Nouvelle Route du Littoral, révélant une zone fragilisée nécessitant une inspection approfondie.

La Réunion – NRL Breakwater Expertise (CLAS)

EGIS, Engineer in charge of design, construction supervision and works acceptance for the construction of the four NRL breakwaters, called on CLAS to assess the abnormally occurring damage on all the structures. The four NRL breakwaters showed abnormal breakages of ACCROPODE™ II units️ units. Neither the engineers of the contractors nor those of the license…

Vue drone de la digue de Kuantan construite avec l’assistance CLAS et certifiée CLASS A BREAKWATER

Kuantan – Certification CLAS (ECERDC)

The construction of the Kuantan breakwater was experiencing difficulties, and abnormal movements accompanied by multiple unit breakages appeared. ECERDC called on CLAS to assess the structure and then supervise the works. Several months were required to finalize the expert assessment of the structure and to formally establish the causes of the defects. This major structure…