Investing in efficiency to secure the project and its operational profitability
CLAS was called in urgently on the Port-la-Nouvelle project to place ACCROPODE™ II and then ECOPODE™ units, in difficult weather conditions that required very fast placement. After eighteen months of works, the outer breakwater was still not protected. CLAS’s experience and methods made it possible to protect it within two months, before the onset of the winter storms. For units of 4 to 14 m³, production reached 6 to 8 units per hour correctly placed underwater; above water, it is considerably higher.
We then set up a permanent placement team, which can work on all other types of units, such as CORE-LOC, Xbloc®, tetrapods and other coastal protection units.
Each team member follows an internal CLAS training programme covering all artificial units used for breakwater armour layers, regardless of brand, generation or configuration.
This offer meets a need clearly expressed by marine contractors and project owners, at a time when public procurement is evolving and increasingly incorporates lessons learned from recent projects.
Experience gained on many projects shows that certain modern technologies, when used without a thorough analysis of their conditions of operational validity, can lead to discrepancies between theoretical assumptions and conditions on site.
These situations are not due to any intrinsic defect in single-layer technologies. They most often result from a lack of understanding of their limits of use, or from the absence of direct and continuous inspection during the placement of the artificial units.
When these limits are not properly identified, the consequences may become visible after the structures are put into service, sometimes reported in the media, and lead to misinterpretations of the reliability of single-layer systems, even though these systems above all require flawless placement quality and appropriate inspection.
ACCROPODE™ and ECOPODE™: registered trademarks owned by the ARTELIA group, which is in no way affiliated with CLAS.
The Project Action Chain for Single-Layer Breakwaters: From Technology Selection to On-Site Implementation
In a typical single-layer armour breakwater project, the chain of responsibilities follows a well-established logic:
– the project owner entrusts the design to a project manager;
– the project manager designs the structure and drafts the tender documents;
– the invitation to tender cites artificial armour unit technologies as a reference, accompanied by the words “or equivalent” or “or similar”, in accordance with public procurement rules, which require openness to equivalent solutions whenever brands are cited. For example, on projects in which CLAS took part:
- the technical specifications (CCTP) for the reinforcement of the north breakwater of the port of Argelès-sur-Mer (project owner: Municipality of Argelès-sur-Mer, 2021) state: “The contractor shall be accompanied by a specific technical party, in connection with the patents of the proposed artificial units (Accropode or equivalent), for external control and placement certification.”;
- the technical specifications for the La Chatière breakwater (project owner: HAROPA PORT, 2023) describe “an outer armour layer of the Accropodes TM type (or equivalent)”;
- the technical specifications for the reinforcement of the western breakwater of Port Gardian (project owner: Syndicat mixte interrégional d’aménagement des digues du delta du Rhône et de la mer, contract no. 2023_08) refer to “the technical specifications of the certifying body for 4 m³ artificial units of the X-BLOCS type or similar”.
Quotations translated from the original French tender documents.
CLAS is in no way affiliated with any of these companies and intervenes on site after a licence agreement has been formalised when one of these trademarked systems is used by the contractor for which CLAS acts as a subcontractor.
– the maritime contractor then selects, according to its strategy, the services required and the contractual context, either a branded system under licence, or a royalty-free solution derived from patents that have expired.
In all cases, the contractor may rely on CLAS for on-site operational support, in addition to any services provided by licence holders, who are neither divers nor maritime construction specialists and do not take part in the actual installation of the armour units on site.
A team of CLAS divers specialising in the placement of artificial armour units places an average of 8 approved units per hour. Client testimonials and our references by armour unit type provide documented evidence of this performance.
The CLAS installation team works with the contractor to define site-specific safety procedures and supports the placement of concrete armour units with a level of productivity and quality control that cannot be achieved without dedicated specialists.
This execution speed significantly limits the exposure of the underlayer and core to wave action, reduces the risk of premature damage, and avoids costly dismantling operations resulting from the late detection of non-compliances.
The time saved thanks to CLAS diver-based installation teams translates directly into improved contractor productivity and overall project cost savings that largely exceed the cost of CLAS intervention.
Understanding the real requirements of single-layer breakwater armour systems
Experience gained on numerous international projects shows that the construction of a breakwater with a single-layer armour made of highly interlocking artificial concrete blocks allows no approximation.
The rules of good practice, as defined by international references (Rock Manual / CEREMA Rock Armour Guide), recall a fundamental principle:
single-layer armour layers are designed for zero damage, including during severe wave events.
In this context, installation quality, effective interlocking of the blocks, and immediate control of non-conformities are decisive factors for the long-term stability of the structure.
Why a specialized team is essential
This technical reality requires a specific site organization.
It calls for a dedicated operational tool, capable of intervening as close as possible to the placement operations, both on the surface and underwater.
It is on the basis of this observation that CLAS has developed a unique approach:
👉 specialized placement teams, directly integrating:
professional divers trained in the installation and inspection of single-layer artificial concrete armour units,
maritime construction experts mastering the geometric, hydraulic and operational constraints of highly interlocking armour layers,
This organization makes it possible to act at the moment when decisions are still reversible, block by block, without waiting for deferred validations.
Technical independence and absence of conflict of interest
CLAS operates in full independence with respect to trademark holders, license vendors, and suppliers of placement and inspection tools.
This independence is a key element of the credibility of CLAS interventions.
It ensures that analyses, recommendations and on-site decisions are based exclusively on:
the rules of good practice applicable to maritime breakwaters,
direct observation of on-site reality,
the technical and economic interest of the project.
It is within this framework that CLAS has been called upon to carry out independent expert assessments, identify the causes of disorders observed on certain structures, and ensure supervision of remedial works when required.
Safety, hyperbaric operations and operational control
To meet the requirements of the most complex projects, CLAS has developed its own underwater intervention capabilities and has become a company certified for hyperbaric operations.
CLAS teams:
include IMCA- and HSE-certified divers,
master modern industrial diving equipment,
apply strict safety procedures and coordination with lifting teams.
Safety is not treated as an administrative constraint, but as a performance lever, making it possible to ensure operational continuity, reduce uncertainties and secure schedules.
Site organization and risk control
Experience shows that advancing the core or the underlayer of a structure without immediate protection by armour units constitutes a major risk, often underestimated.
An unprotected structure remains exposed to the first significant storm, with possible consequences such as:
partial destruction of the works in progress,
loss of achieved progress,
accumulated delays and significant cost overruns.
CLAS teams support contractors in the definition of realistic site strategies, adapted to the site conditions, available resources and scheduling constraints, in order to secure each critical phase of construction.
A profitable investment for contractors
Calling on a CLAS team does not represent an additional expense, but a directly profitable investment.
The presence of specialized teams makes it possible to:
limit costly dismantling and rework operations,
improve actual on-site productivity,
reduce technical and contractual risks,
secure the final quality of the structure.
This approach contributes to better overall economic control of the project, while guaranteeing the technical compliance of maritime breakwater armour layers.
Choosing a CLAS team means choosing:
operational safety,
impeccable installation quality,
control of technical risks,
and sustainable project profitability.
CLAS supports maritime contractors with a pragmatic, independent approach, grounded in real on-site experience.
