The construction site for the protection breakwater of the water intakes of the BARAKAH nuclear power plant in Abu Dhabi had been halted.
NMDC was required to place 110,000 CORELOC units on this project. The use of the POSIBLOC™ system led to the refusal of placement and to delays on the construction site. IDMer, now CLAS, intervened on an emergency basis.
POSIBLOC™ is a registered trademark owned by MESURIS, which is in no way affiliated with CLAS.
The POSIBLOC™ systems were stopped and replaced by divers whom we trained.


The mission entrusted to CLAS
Train the installation teams,
Supervise the works,
Improve installation quality,
Achieve high production,
NMDC testimonial
Here is the strictly faithful translation into US English, without reformulation and preserving the structure:
We hereby confirm that the ID Mer team, composed of Mr. Eric SKIERNIEWSKI, Mr. Pascal JARD and Mr. Dimitri STRELETSKY, was involved in our Baraka (Barakah) nuclear power plant project and carried out the following daily diving activities:
Supervision of diving operations for the installation of the artificial armor – Core-Loc
Inspection of the placement of the artificial armor – Core-Loc
Installation of the artificial armor – Core-Loc
Training of diving teams for the installation of the artificial armor – Core-Loc
Supervision and execution of airlift operations
Supervision and execution of the placement of the toe armor in 1–3T rock
Presentation to the Client of the working methodology for approval of the execution methods
The intervention of ID Mer was of an exemplary level, and its services gave full satisfaction on our project.
ID Mer was present on site from May 2013 to February 2014.