Argelès-sur-Mer – CLAS Training, Assistance and Certification (Buesa – Razel – TDA)

The BUESA–RAZEL–TDA consortium chose the BS2 unit to reconstruct the Argelès-sur-Mer breakwater.

The BS2 unit can be used without paying a license fee by adhering to the BREAKWATER SOLUTION™ trademark and quality charter registered by CLAS, in order to enable contractors to respond to public tenders with a royalty-free alternative.

Bloc BS2 libre de droits mis en œuvre sur la digue d’Argelès-sur-Mer
Vue drone de la digue d’Argelès en construction avec la mise en œuvre des blocs BS2.

The mission entrusted to CLAS

Assist the consortium during the study phase of the work procedures,

Prepare the placement drawings,

Train the personnel in safety,

Train the personnel in the installation of BS2 units,

Provide full-time support to the consortium with a CLAS team,

Certify the quality of the works.

Testimonial from the consortium of companies

I, the undersigned Ahmed HELALI, holding the position of Project Director for the reconstruction of the Argelès-sur-Mer breakwater, within the company BUESA, acting as lead contractor, hereby certify that the company CLAS SLU gave us full satisfaction in the execution of the tasks entrusted to it.

These services concerned:

Technical assistance to BUESA for the reconstruction of the armor layer of the Argelès-sur-Mer breakwater.

The mission entrusted to CLAS included in particular the following items:

Provide on-demand assistance during the study phase of technical solutions.

Prepare the placement drawings for the newly installed BS2 artificial units and for the existing units that were removed and reinstalled.

Ensure follow-up of safety training for personnel.

Provide full-time assistance during the construction phase.

Achieve or exceed the production objectives.

Achieve the quality objectives.

Optimize construction costs.

Prepare the quality certification file for the Engineer in charge of design, construction supervision and works acceptance and the Owner.

The company CLAS fulfilled its mission in a professional manner and met the deadlines assigned to it.