Drone aerial view of concrete armour unit installation on the offshore breakwater at Port-La-Nouvelle, France

Testimonial – Bouygues, Port-La-Nouvelle Port (France)

Bouygues urgently called on CLAS to carry out the installation of concrete armour units. The offshore breakwater had been severely damaged three times by winter storms and, despite the procedures and equipment deployed, including POSIBLOC™, multibeam sonar and digital twin tools, the works were not progressing as expected. After 18 months of sustained efforts, the…

Concrete armour units stored on a barge prior to installation on a port breakwater

Testimonial – Van Oord, Constanta breakwater(Roumanie)

Van Oord appointed CLAS to provide technical support on the Constanța port extension project in Romania. During the Constanța port protection project in Romania, CLAS teams worked alongside Van Oord, providing specialized support for the installation of ACCROPODE™II concrete armour units and independent certification of the breakwater armour layer. The mission entrusted to CLAS Technical…

Vue drone de la digue de La Turballe inspectée et documentée par CLAS

La Turballe Breakwater – CLAS Support and Certification

CHARIER called on CLAS to assist during the extension of the La Turballe breakwater. To call on the expertise of CLAS. All stakeholders involved in this project wished to obtain Class A certification for this major structure. CLAS intervened to achieve this objective. The placement of the X-bloc® units was carried out by divers. X-bloc®…

CLAS contrôle la pose des blocs sur le chantier de Barakah

Barakah – CLAS Assistance and Certification (NMDC)

The construction site for the protection breakwater of the water intakes of the BARAKAH nuclear power plant in Abu Dhabi had been halted. NMDC was required to place 110,000 CORELOC units on this project. The use of the POSIBLOC™ system led to the refusal of placement and to delays on the construction site. IDMer, now…

Vue drone de la digue de Kuantan construite avec l’assistance CLAS et certifiée CLASS A BREAKWATER

Kuantan – Certification CLAS (ECERDC)

The construction of the Kuantan breakwater was experiencing difficulties, and abnormal movements accompanied by multiple unit breakages appeared. ECERDC called on CLAS to assess the structure and then supervise the works. Several months were required to finalize the expert assessment of the structure and to formally establish the causes of the defects. This major structure…

Chantier de Ras Laffan au Qatar avec assistance des experts CLAS

Ras Laffan – CLAS Assistance and Training (CFE Qatar)

The company CFE QATAR was unable to construct the breakwater armor layer. The company IDMer, now CLAS, intervened on an emergency basis. CFE QATAR was using the POSIBLOC™ system. Placement was being rejected and the construction site was exposed to delay penalties. Approximately 40,000 ACCROPODE™ units had to be installed… a challenge that our experts…