Marina Solidere Beyrouth

Le projet

YEAR: 2019–2020
PROJECT: New Beirut Marina – Solidere
COMPANY: ./
CLIENT : Solidere

Plongeur CLAS inspectant sous l’eau la carapace d’une digue pour vérifier l’imbrication et la stabilité des blocs.
Vue d’une digue de la marina de Beyrouth certifiée Classe A par CLAS après contrôle complet de la carapace et de l’imbrication des blocs.

Background

The Eastern Marina project consisted of the construction of the new marina in Beirut, Lebanon. Solidere, as Project Owner, entrusted the design to DAR and the construction works to ARACO.
CLAS was appointed to supervise the entire construction works and to implement quality certification, ensuring the technical compliance and durability of the structures built with ACCROPODE™ concrete armour units.

ACCROPODE™ is a registered trademark owned by the ARTELIA group, which is in no way affiliated with CLAS.

CLAS intervened on this project in full independence from the licence seller.

Key figures

Travail en cours sur le chantier de construction de la digue, supervisé par les experts CLAS pour garantir la qualité de mise en œuvre.

Role of CLAS

  • Implement the CLAS certification procedures for construction quality.

  • Supervise the installation works and quality control operations.

  • Achieve the production objectives set by the Project Owner.

Remise du certificat CLASS A BREAKWATER par CLAS aux représentants de SOLIDERE pour la digue de la marina de Beyrouth.

Result

The ACCROPODE™ structures built under the supervision of CLAS were certified “CLASS A”. They are located in the area directly impacted by the 2020 Beirut Port explosion.
The joint expert assessment carried out after the explosion confirmed that no damage was observed: no broken, displaced or destabilised units were identified.
This outcome illustrates the robustness and quality of the construction works and of the supervision performed by CLAS, carried out with no connection whatsoever to the licence sellers.