ACCROPODE™ II 6 m3 = 3590 units.
ACCROPODE™ II 8 m3 = 9490 units.
ACCROPODE™ II 11 m3 = 6540 units.
The four breakwaters of the Nouvelle Route du Littoral exhibited ACCROPODE ™ II breakages in an unusual proportion.
CLAS was commissioned to carry out an aexpertise of the four ACCROPODE ™ II breakwaters and determine the causes of this breakages.
The expertise made it possible to explain the causes of the breakages and to submit a detailed risk assessment to the EGIS Project Manager and to the client Réunion Région.
COMMENTS FROM EGIS