YEAR: 2012ECOPODE Expertise pose ECOPODE placement ecopode ospedaletti

PROJECT: PORT D'OSPEDALETTI

COUNTRY: ITALY

CONTRACTOR: /

CLIENT: FINIM

 

 

 

HISTORY:ECOPODE Expertise pose ECOPODE placement ecopode ospedaletti

 

IDMer, which has become CLAS, has been engaged as an expert to make an inventory of the port of OSPEDALETTI whose construction work has been stopped.

 

 

 

 

 

ECOPODE Expertise pose ECOPODE placement ecopode ospedalettiKEY FIGURES:

ECOPODE ™ 4 m3 730

ECOPODE ™ 6 m3 1419

ECOPODE ™ 8 m3 676

 

ACCROPODE ™ II 4 m3 354

ACCROPODE ™ II 6 m3 902

ACCROPODE ™ II 8 m3 611

 

 

 

 

 

 

 

 

 

MISSION:ECOPODE Expertise pose ECOPODE placement ecopode ospedaletti

IDMer, now CLAS, intervened as an expert with mission:

 

Project visit, inspection of the installed ECOPODE ™ and    ACCROPODE ™ II.

Identification of non-conformities and progress of works.

Report to FINIM.

 

 

ECOPODE Expertise pose ECOPODE placement ecopode ospedalettiPROCEDURE:

Classic inspection procedure by diver and by boat.

 

 

 

 

 

 

ECOPODE Expertise pose ECOPODE placement ecopode ospedaletti

RESULT:

 

The non-conformities were identified and a detailed report with risk analysis sent to FINIM.

 

 

 

 

 

 

CLAS continues this tradition of excellence and security at the service of your projects

 