YEAR: 2017
PROJECT: ALFAW WESTERN BREAKWATER
COUNTRY: IRAQ
CONTRACTOR: DAEWOO
CLIENT: GOVERNMENT
HISTORY:
DAEWOO had to build a new portnear BASSORA. CLAS provided training for DAEWOO on site for one month.
THE KEY NUMBERS :
93,000 CORELOC ™ of 1.4 m3 and 3 m3.
THE MISSION :
CLAS intervened to train DAEWOO teams in the installation of CORELOC ™:
Train CORELOC ™ laying teams.
Ensure the interface between the company and CLI.
PRODUCTION:
Production is calculated on the basis of actual installation hours. Stoppages due to bad weather, breakdowns and generally causes unrelated to the installation of CORELOC ™ are not taken into account in this calculation.
CORELOC ™ 1.4 m3: 15 units per hour for direct visual installation.
3 units per hour with POSIBLOC ™.
PROCEDURE:
CLAS inspectors worked full time for one month.
RESULT:
When CLAS left the project after a month of training in CORELOC ™ technology, the DAEWOO teams were perfectly in control of visual installation.
DAEWOO COMMENT:
CLAS continues this tradition of excellence and security at the service of your projects