YEAR: 2010-2011
PROJECT: MARCHICA
COUNTRY: MOROCCO
CONTRACTOR: SOMAGEC
CLIENT: GOVERNMENT
HISTORY :
The company SOMAGEC was to deliver the project in May 2011 for a royal visit.
The SOMAGEC subcontractor responsible for installing the ACCROPODE ™ II was unable to install quickly enough.
SOMAGEC called upon IDMer, now CLAS.
KEY FIGURES:
5,000 ACCROPODE ™ II from 2 to 5 m3.
MISSION:
Install 5,000 ACCROPODE ™ II approved in two months.
Quality certification based on inspections and videos showing respect for design, CLI TID and above all the very good nesting of ACCROPODE ™ II blocks.
PRODUCTION:
We applied 15 ACCROPODE ™ II / hour on average.
PROCEDURE:
CLAS inspectors installed ACCROPODE ™ II themselves to meet this very short deadline.
RESULT:
5,000 ACCROPODE ™ II were installed and approved in 45 days, despite breakdowns and stops caused by the weather.
SOMAGEC COMMENT:
This very badly started work ended in giving us full satisfaction and we came back on our negative opinion about ACCROPODE ™ II. As long as we have efficiency and quality of this level, we will not hesitate to offer the ACCROPODE ™ II as a variant for future projects.
To go in this direction we asked Mr. SKIERNIEWSKI to provide for the training of a team of SOMAGEC divers and technicians, so that our company remains the leader in maritime works in Morocco and acquires reasonable autonomy in the ACCROPODE ™ II installation techniques, supplemented by a quality certification of that implemented at Marchica.
CLAS continues this tradition of excellence and security at the service of your projects