YEAR: 2018-2020
PROJECT: EASTERN MARINA
COUNTRY: LEBANON
COMPANY: ARACO
CLIENT: SOLIDERE
HISTORY:
SOLIDERE was to build the NEW MARINA in BEIRUT. SOLIDERE entrusted the design work to DAR and the construction work to ARACO. SOLIDERE awarded CLAS a contract to supervise all the works and a certification of the quality.
KEY FIGURES:
2457 ACCROPODE™ of 12 m3.
MISSION:
Implement certification procedures.
Achieve quality and production goals.
PRODUCTION:
ARACO placed 6 ACCROPODE ™ / hour on average.
PROCEDURE:
We inspected the work several times a day.
We have carried out the certification procedures.
RESULT:
ACCROPODE ™ structures built under the supervision of CLAS
Are located in the area affected by the explosion at the Port of Beirut.
The joint expert appraisal carried out after this explosion confirmed that there was no
no effect on the works.
No broken, destabilized or extracted ACCROPODE ™.
The works have been certified "CLASS A".
SOLIDERE'S COMMENT:
The CLAS company perpetuates this tradition of excellence and safety in the service of your projects