VAN OORD CORELOC™ AL ZOUR KUWEIT

CLAS intervened on the AL ZOUR project in KUWAIT at the request of VAN OORD.

We have carried out the certification of the installation of CORELOC.

 

The advice given to the installation team and the inspection procedure several times a day implemented by CLAS allowed VAN OORD to reach the average production of 100 CORELOC per day approved with only one placing team.

 

 

VAN OORD and his client were satisfied and CLAS received the following testimony: